Friday, October 29, 2010

Driveway Poured & First Wall Up

Friday, October 29, 2010
The cement work is done!  Sidewalk from driveway to front door and driveway poured.  Window wells are about 75% done.  Load bearing wall in basement is up.





Tuesday, October 26, 2010

Driveway Prep & Window Well

Monday, October 25, 2010
Driveway rebar laid, sidewalk to front door rebar laid.  Forms for sidewalk and drive way ready to go.  Window well started.  Ordered windows and got shingle and siding samples. 
Nothing new until the rain (or snow?!) stops, now

Friday, October 22, 2010

Concrete Poured

Friday, October 22, 2010
Basement floor, Garage floor, and approach concrete poured


Thursday, October 21, 2010

Front Yard and Garage Fill

Thursday, October 21, 2010
Front yard is back filled and garage is filled. 


Wednesday, October 20, 2010

Basement Floor Plumbing

Wednesday, October 20, 2010
Plumbing done under the basement concrete floor

Water Sealant Applied

Monday, October 18, 2010
Tar water sealant applied to concrete basement walls

Wall Forms Removed

Friday, October 15, 2010
Concrete forms removed - we have basement walls