Sunday, February 20, 2011

Lights, cabinets, trim, etc.

Feb 14-18, 2011
Cabinets/countertops delivered.  Most cabinets/countertops installed.  Window and door trim worked on.  All doors installed by the end of the week.  Most window and door casings in place, too.  Basement walls done - tape, texture, white paint.  Stairs in garage into house done.







Feb 7-11, 2011
Electricians were back - installed the outlets and light switches, recessed lights and the chandelier.  Tape and texture work started on the basement.  Cabinets delivered.  More work on the siding.  Doors delivered.  Some doors installed.